MACKAY RIVER PROJECT

150,000 bpd SAGD operation

2011 Q4: received regulatory approval

2012 Q1: started Phase 1 of construction

2016 Q3: achieved mechanical completion

2016 Q4: achieved first steam

2017 Q3: achieved first oil to market